This week, Construction continued assembling mechs, with the finished ones getting mounted onto the floats. Yesterday, steel was cut at the lab in San Luis Obispo and driven down this morning to prepare for. Hydraulics removed the main pump from the float, closing leaks and fixing the steering. Electronics continued testing animation controls, the overheight safety sensor, and the 12 volt distribution box. Design finished up their frog legs and robot legs, cleaning the lab along the way, while Pod continued building structures, and Concealment started carving heliconia, lily, and hibiscus bulbs. Decorations started fresh testing the macaw, and working on butterfly pattern testing. Operations continued their projects, preparing the merch store, and assisting the Collins College of Hospitality Management in serving food.